Bull Moose Tube
SCM, Inc. has performed several turnkey projects for Bull Moose Tube. The first project involved relocating a slitter line, tube mill, and steel stacking system from Elkhart, IN to Trenton, GA. We accomplished this within a strict 46-day timeframe. This was the first time that Bull Moose Tube relocated a mill and met their start-up date. This milestone enabled SCM, Inc. to form a long-lasting relationship with Bull Moose Tube.
Over the years, SCM, Inc. has installed the following at Bull Moose Tube:
- Slitter systems (consisting of turnstiles, unwind stands, straighteners, finished metal roll-up, and scrap roll-up)
- Conveying systems
- Stacking conveying systems
- Kasto saw lines
- Package lines
- Overhead cranes
- Machine shops
View more Bull Moose Tube projects and details

Client:
Location:
Project Duration:
Value:
Bull Moose Tube
Trenton, GA
46 Days
$1.5 Million