Fort Stewart Barracks Complex -
Phase 2
Type of Facility
- Barracks Complex
Scope of Project
The Sack Company performed a complete electrical and plumbing installation for this new barracks complex on Fort Stewart. This $33.9 million complex is being built in order to provide housing opportunities for members of the 2nd Brigade Combat Team – Third Infantry Division. Each of the four 19,500 sq. ft. buildings will house 48 soldiers.

Client:
Location:
Contractor:
Architect:
Project Duration
Value:
U.S. Army COE, Savannah District
Ft. Stewart, GA
B.L. Harbert
Cooke Douglass Farr & Lemons
18 months
$3.6 Million